The installation of the work was planned to take place on the 18th and the 19th of April but this extended it into the forthcoming week.
My partner and me managed to position the speakers on all four walls but we couldn’t install the full equipment as two of the outputs were faulty and had to be returned and exchanged.
The new equipment eventually arrived on Tuesday the 21st and we continued with the set up. For the next 9 days I was wiring the speakers and gluing the cables to the walls (as I was not aloud to fix the cables to the walls I had to use silicon glue gun to secure them).
Although everything was booked weeks in advance there were still many problems.
Literally my troubles continued, constant complains from some of the staff, double bookings of dates… I had to move the equipment from the chapter house to an electric cabin near by, and although all the cables were very neatly positioned there was still not satisfaction! I guess some people are never satisfied and they’ll never be happy no matter what you do they’ll always find something to complain about!